What a Carbon Reduction Plan is

A Carbon Reduction Plan, or CRP, is a plan you write once a year and publish on your own website. It records three things: a commitment to reach net zero by 2050 at the latest, how much carbon your business emits now compared with a baseline year, and the targets and projects that will bring that figure down.

It is written by you and signed off by a director. It is not a certificate, nobody awards it and it does not need to be audited. Its job is to show a buyer, in a standard format, that you measure your emissions and have a plan to reduce them.

Who asks for it

Central government departments, their executive agencies and non-departmental public bodies.

The standard

PPN 006, published by the Cabinet Office on GOV.UK. It replaces PPN 06/21 and does not change the policy.

Who writes it

You do. It is self-declared and signed by a director or equivalent.

Who needs one

PPN 006 applies to contracts for goods, services or works with an estimated value above £5 million a year including VAT, averaged over the life of the contract, bid for under the Procurement Act 2023. For frameworks and dynamic markets it applies only where the individual contract is above £5 million a year. It applies to relevant procurements advertised on or after 24 February 2025; earlier ones stay under PPN 06/21.

The plan is a condition of participation. The buyer uses it to judge your technical ability, and asks for it in a way that is relevant and proportionate to the contract.

Even where no contract strictly requires one, a published plan is increasingly asked for in tenders, supplier questionnaires and ESG reviews, so many suppliers write one before they are asked.

What goes in a Carbon Reduction Plan

The government template has a header with your name and the publication date, then seven sections.

The seven sections of the PPN 006 template
SectionWhat it covers
Commitment to achieving net zeroA commitment to reach net zero by 2050 at the latest.
Baseline emissions footprintYour emissions in a baseline year: Scope 1, Scope 2 and the required Scope 3 categories.
Current emissions reportingYour emissions for the latest reporting year, set out the same way as the baseline.
Emissions reduction targetsThe targets you have set to cut emissions from the baseline.
Carbon reduction projectsMeasures already completed, and measures planned for the future.
Declaration and sign offA statement that the plan follows the technical standard.
Signed on behalf of the supplierA named director, or equivalent senior person, with the date.

Emissions are reported in tonnes of carbon dioxide equivalent (tCO2e) for Scope 1 (fuel you burn), Scope 2 (energy you buy) and the required Scope 3 categories (emissions in your wider supply chain). The baseline and current sections are the heart of the plan, so it pays to keep your figures tidy from the start. Our Track my carbon page shows how to compare the two.

The five Scope 3 categories PPN 006 requires

Of the 15 Scope 3 categories defined by the Greenhouse Gas Protocol, PPN 006 requires these five.

Scope 3 categories required by PPN 006
CategoryWhat it covers
Category 4Upstream transportation and distribution
Category 5Waste generated in operations
Category 6Business travel
Category 7Employee commuting
Category 9Downstream transportation and distribution

Not sure where to begin? Read Scope 3: where to start.

How to write a Carbon Reduction Plan

  1. Pick your baseline year. Choose a recent twelve-month period for which you have reliable records, and keep it fixed. Every later year is compared with it.
  2. Gather your activity data. Fuel used, electricity and gas, business miles, waste, commuting and distribution. Invoices and meter readings are the usual sources.
  3. Convert it to emissions. Multiply each activity by the matching emission factor from the UK government conversion factors, and add up Scope 1, Scope 2 and the five Scope 3 categories in tCO2e.
  4. Repeat for the current year. Use the same method, so the two years can be compared fairly.
  5. Set your targets and projects. Say what you have already done to cut emissions and what you plan to do, with targets measured from your baseline.
  6. Commit to net zero. State a net zero date of 2050 or earlier.
  7. Get it signed. A director, or equivalent senior person, signs the declaration with their name and the date.
  8. Publish it. Put the plan on your UK website and link to it from a prominent place on your homepage.
  9. Update it every year. Review and update it within six months of your financial year end.

Common mistakes

  • Treating carbon neutral as net zero. They are different. PPN 006 asks for a net zero commitment by 2050 at the latest.
  • Sending the plan to the buyer but not publishing it. It has to be on your website, clearly signposted.
  • Publishing once and forgetting it. A plan that is more than a year old can look out of date to a buyer.
  • Using different methods for baseline and current year. The comparison only means something if both years are worked out the same way.
  • Leaving out the sign-off. A plan with no named director and date is incomplete.

Common questions

What is a Carbon Reduction Plan?

A Carbon Reduction Plan (CRP) is a short document in which a supplier sets out its carbon footprint, its commitment to reach net zero and the steps it is taking to cut emissions. UK government asks for one from suppliers bidding for major contracts, under PPN 006 (formerly PPN 06/21).

Is a Carbon Reduction Plan the same as a net zero plan?

Not exactly. A CRP includes a net zero commitment, but it also has to report your baseline and current emissions and say what you are doing to reduce them. It is a report on where you are, not only a promise about where you want to be.

Do I need to have my carbon footprint audited?

No. The PPN 006 technical standard says there is no requirement to have your carbon footprint audited. The plan is written and signed off by the supplier, so it is self-declared.

Do I have to report all 15 Scope 3 categories?

For PPN 006, five Scope 3 categories are required. NHS England's 2027 requirements ask for all relevant Scope 3 emissions, so check what the buyer you are bidding to expects.

Where do I publish my Carbon Reduction Plan?

On your own UK website, clearly signposted. The technical standard asks for a link in a prominent place on your homepage. If you have no website, you must give a written copy to anyone who asks within 30 days.

How often must I update it?

At least once a year. The technical standard asks for the plan to be reviewed and updated within six months of your financial year end.

Does having a Carbon Reduction Plan mean I have been approved?